By Kyle Roberts
RUSTON, La. — The Lincoln Parish School Board Finance Committee met Thursday at 2 p.m. at the main school board office and voted to send a $7,650,563 funding recommendation for the Lincoln Parish Early Childhood Center renovation project to the full board, along with a related $5.4 million fund transfer.
The committee’s only agenda item was consideration of the guaranteed maximum price, or GMAX, for the LPECC renovations.
“This was an important step in finalizing the funding related to the LPECC renovation,” LPSB Superintendent JohnYoung said. “I’m thankful to our finance committee and business department for formulating a plan forward that allows our district academics and operations to consolidate into one location.”
Young gave the background. The board authorized use of the Construction Management at Risk service for the project at its March 3 meeting. After a bid process, Triad Builders of Ruston Inc. was selected. Young said the district met with Triad and Walpole Architects and settled on two pieces of work: converting the LPECC building into office space and building a new maintenance and storage facility, with space for buses, on the site.
Young said the district received the GMAX from Triad on Wednesday: $6,612,426. Pricing was discussed in three meetings, Young said. The first price, on Aug. 13, was higher, and a second, on Oct. 6, was $6,873,485. The district made modifications along the way to reach the final figure.
The recommended total of $7,650,563 includes the GMAX plus fees for architectural and engineering services and miscellaneous owner costs. Young listed those costs as furniture, workstation cubicles, a telephone system upgrade, appliances, computers, copiers, wiring, smart boards, televisions, monitors, shelving, generators, access control systems and pallet racks for the maintenance facility. Young said the district plans to reuse furniture and generators from the current building to hold costs down, and that a new board room will need to be furnished.
The office space would house district employees now based at the central office, along with transportation, special education and other staff, Young said, putting them under one roof.
Young added that a $3 million item to restore track and field event areas at Ruston High School is also part of the capital plan. Young said the pavilion was built over the javelin, shot put, discus, long jump, high jump and triple jump areas, and that Ruston High currently cannot host a track meet. Young also said Simsboro’s track needs resurfacing within the next year.
Young said he would like community input on the future of the current building and would prefer it remain a community asset. He said the project is expected to take 10 to 12 months, with a first shovel possibly going in the ground in January, and that security systems would stay on at the old building.
“I look forward to engaging with our board and stakeholders to determine what the future holds for our Farmerville Street property,” Young said.
The committee added the $5.4 million transfer to the motion. Of that amount, $4 million would come in 2026-27 and $1.4 million in 2027-28.
Young said members will see the final plans before that vote.
“The full board will have an opportunity to see those final plans for funding and renderings prior to our regularly scheduled meeting on December 1,” Young said. “Our focus remains on improving student outcomes, and our board recognizes the importance of doing that.”

Source: lincolnparishjournal.com